Document Actions

Improvement District 7 - Kamakee Street Extension

Kamakee ID-7

This $11 million project involved infrastructure improvements and a realignment of Kamakee Street (from Queen Street to Kewalo Basin) and creation of a four-way signalized intersection at Ala Moana Boulevard and Ala Moana Park Road. These major improvements involvd: the installation of water, sewer and drainage systems; the widening of roadways; the construction of curbs, gutters and sidewalks; and the undergrounding of electrical and telephone lines.

The ID-7 Project constructed improvements to the last major segment of the drainage system for Kakaako's Mauka Area. The Kamakee Street improvements and realignment greatly improves traffic circulation through the Kakaako District and created a new, direct link between Kakaako and the Ala Moana Beach Park.

Construction of the ID-7 project began in November 1999. The project was completed by early 2002.